Little London level crossing

Manually-controlled barrier with obstacle detection level crossing on the North and East route (ELR MAC3).

right now
OPEN
for at least 2h

Next 30 min

OPEN 01:14–03:14+ 2h+
Under the hood
Fri 24 Jul · 01:14
Today Tomorrow

Trains in window

No trains in the next 30 minutes.
now 01:14:57 · 77 avg · 0 in window
lx berths down: Y0/8631→Y0/[email protected] · up: Y0/8646→Y0/[email protected]
timetable cif full+upd 2026-07-22..2026-07-24
fetched 23:44:56
trust 33,087 active · 30,126 delays · 1,797 cancelled · 0 reconnects
Nearby crossings

All 867 crossings in Eastern →

About this crossing

How often it closes

On today’s timetable, Little London crossing is predicted to be closed for about 4 h 23 min between 06:00 and 22:00, across roughly 51 closures. The longest single predicted closure is 11 minutes. Freight paths scheduled “as required” — most don’t run on any given day — aren’t counted here; when one does run, the live timeline above shows it.

Worst times to cross today

Closures cluster around 06:46–07:46 in the morning and around 12:37–13:37 in the middle of the day. Gaps between closures are longest outside those windows. Other days run a different timetable, so the peaks move.

About this crossing

Little London is a manually-controlled barrier with obstacle detection crossing (MCBOD) on the Cleethorpes–Barton-on-Humber line (North and East route · ELR MAC3). An obstacle-detection system scans the crossing and confirms it is clear before the barriers lower automatically. Forecasts here combine the working timetable with live train-movement data (and live signalling where the crossing has it), so they reflect actual running including delays and freight — though they can still be wrong when the network is disrupted.

How accurate is this forecast?

We score this page against what actually happened on the railway — over the last 7 days that covered 4 trains through this crossing.

100.0% of observed passes were being warned about on this page when they passed, and 100.0% of the warnings we could verify came true.

Typical timing error was ±18s (9 in 10 within 391s). This scores when trains pass — barrier movements aren't in the public feeds we can score against.

Full accuracy report →

Is this right?