Whitehouse level crossing

Manually-controlled barrier with obstacle detection level crossing on the North and East route (ELR DSN2).

predicted
OPEN
for 5 min

Information only — always follow the signals and barriers at the crossing. Predictions may be wrong.

next: 🚄 in 8 min · 1 min late

Next 30 min

OPEN 06:26–06:31 5m
CLOSED 06:31–06:37 6m
OPEN 06:37–06:51 14m
CLOSED 06:51–06:55 3m
OPEN 06:55–07:01 → 7m
Under the hood
Tue 06 Oct · 06:26
Today Tomorrow

Trains in window

06:17 🚛 4N14 Doncaster Iport GBRF → Tees Dock GBRF Down (W → E) no show
06:34 🚄 1N53 Saltburn → Newcastle Up (E → W) +1 min
06:35 🚆 2D04 Darlington → Saltburn Down (W → E) approaching
06:37 🚄 1N57 York → Redcar Central Down (W → E) on time
06:44 🚛 6D11 Tees Dock BSC Export Berth → Gascoigne Wood Up (FHH) Down (W → E) sched
06:54 🚆 2D06 Darlington → Saltburn Down (W → E) -1 min
🚄Express passenger 🚆Passenger 🚛Freight
now 06:26:34 · 197 avg · 6 in window
live observation: 1 up · 2 down
timetable cif full+upd 2026-10-05..2026-10-07
fetched 02:08:18
trust 33,306 active · 31,624 delays · 1,668 cancelled · 0 reconnects
Nearby crossings

All 866 crossings in Eastern →

About this crossing

How often it closes

On today’s timetable, Whitehouse crossing is predicted to be closed for about 7 h 15 min between 06:00 and 22:00, across roughly 85 closures. The longest single predicted closure is 9 minutes. Freight paths scheduled “as required” — most don’t run on any given day — aren’t counted here; when one does run, the live timeline above shows it.

Longest closure so far today: 5.9 min (05:47–05:53, 1 train), timed from trains actually seen on the signalling wire — the window edges use the same per-type margins as the forecast, since barrier positions aren't in any feed we can read.

Worst times to cross today

Closures cluster around 06:24–07:24 in the morning and around 13:33–14:33 in the middle of the day. Gaps between closures are longest outside those windows. Other days run a different timetable, so the peaks move.

About this crossing

Whitehouse is a manually-controlled barrier with obstacle detection crossing (MCBOD) on the Middlesbrough–Wilton EFW Terminal line (North and East route · ELR DSN2). An obstacle-detection system scans the crossing and confirms it is clear before the barriers lower automatically. Forecasts here combine the working timetable with live train-movement data (and live signalling where the crossing has it), so they reflect actual running including delays and freight — though they can still be wrong when the network is disrupted.

How accurate is this forecast?

We score this page against what actually happened on the railway — over the last 7 days that covered 408 trains through this crossing.

100.0% of observed passes were being warned about on this page when they passed, and 99.6% of the warnings we could verify came true.

Typical timing error was ±161s (9 in 10 within 260s). This scores when trains pass — barrier movements aren't in the public feeds we can score against.

Full accuracy report →

Is this right?