Thorpe Gates level crossing

Manually-controlled barrier with obstacle detection level crossing on the North and East route (ELR HUL3).

predicted
OPEN
for 2 min

Information only — always follow the signals and barriers at the crossing. Predictions may be wrong.

next: 🚆 in 5 min · 4 min late

Next 30 min

OPEN 09:22–09:24 2m
CLOSED 09:24–09:27 3m
OPEN 09:27–09:30 3m
CLOSED 09:30–09:33 3m
OPEN 09:33–09:36 3m
CLOSED 09:36–09:39 3m
OPEN 09:39–09:48 9m
CLOSED 09:48–09:52 4m
OPEN 09:52–10:04 → 12m
Under the hood
Mon 07 Sep · 09:22
Today Tomorrow

Trains in window

09:27 🚆 2K08 HalifaxHull Down (W → E) +4 min
09:33 🚆 2R72 BridlingtonYork Up (E → W) +1 min
09:39 🚄 1K12 HullLiverpool Lime Street HL/ML Up (E → W) +1 min
09:51 🚆 2K11 HullHalifax Up (E → W) on time
09:52 🚄 1K11 Liverpool Lime Street HL/MLHull Down (W → E) +6 min
🚄Express passenger 🚆Passenger
now 09:22:36 · 125 avg · 5 in window
live observation: 1 up · 0 down
timetable cif full+upd 2026-09-06..2026-09-08
fetched 02:08:15
trust 49,497 active · 28,141 delays · 3,112 cancelled · 0 reconnects
Nearby crossings

All 866 crossings in Eastern →

About this crossing

How often it closes

On today’s timetable, Thorpe Gates crossing is predicted to be closed for about 6 h 46 min between 06:00 and 22:00, across roughly 93 closures. The longest single predicted closure is 7 minutes. Freight paths scheduled “as required” — most don’t run on any given day — aren’t counted here; when one does run, the live timeline above shows it.

Longest closure so far today: 3.2 min (05:39–05:43, 1 train), timed from trains actually seen on the signalling wire — the window edges use the same per-type margins as the forecast, since barrier positions aren't in any feed we can read.

Worst times to cross today

Closures cluster around 07:52–08:52 in the morning and around 12:03–13:03 in the middle of the day. Gaps between closures are longest outside those windows. Other days run a different timetable, so the peaks move.

About this crossing

Thorpe Gates is a manually-controlled barrier with obstacle detection crossing (MCBOD) on the Micklefield–Selby line (North and East route · ELR HUL3). An obstacle-detection system scans the crossing and confirms it is clear before the barriers lower automatically. Forecasts here combine the working timetable with live train-movement data (and live signalling where the crossing has it), so they reflect actual running including delays and freight — though they can still be wrong when the network is disrupted.

How accurate is this forecast?

We score this page against what actually happened on the railway — over the last 7 days that covered 355 trains through this crossing.

100.0% of observed passes were being warned about on this page when they passed, and 99.6% of the warnings we could verify came true.

Typical timing error was ±63s (9 in 10 within 267s). This scores when trains pass — barrier movements aren't in the public feeds we can score against.

Full accuracy report →

Is this right?