CCTV-monitored manual barrier level crossing on the East Coast route (ELR DOL1).
Information only — always follow the signals and barriers at the crossing. Predictions may be wrong.
| 18:03 | 🚆 2B25 | Leeds → Doncaster Up (N → S) | +1 min |
| 18:13 | 🚄 1A30 | Leeds → London Kings Cross Up (N → S) | +2 min |
| 18:14 | 🚃 5R55 | Doncaster → Doncaster Down (S → N) | active |
| 18:20 | 🚄 1D23 | London Kings Cross → Harrogate Down (S → N) | on time |
| 18:27 | 🚆 2B80 | Doncaster → Leeds Down (S → N) | active |
| 18:30 | 🚆 2R53 | Adwick → Sheffield Up (N → S) | active |
| 18:36 | 🚛 6E83 | Horton in Rib Quarry GBRf → Doncaster Down Decoy GBRF Up (N → S) | no show |
| 18:40 | 🚄 1A31 | Bradford Forster Square → London Kings Cross Up (N → S) | on time |
On today’s timetable, Dock Hills crossing is predicted to be closed for about 8 h 56 min between 06:00 and 22:00, across roughly 106 closures. The longest single predicted closure is 9 minutes. Freight paths scheduled “as required” — most don’t run on any given day — aren’t counted here; when one does run, the live timeline above shows it.
Closures cluster around 10:15–11:15 in the morning and around 14:01–15:01 in the afternoon. Gaps between closures are longest outside those windows. Other days run a different timetable, so the peaks move.
Dock Hills is a cctv-monitored manual barrier crossing (CCTV) on the Doncaster–Adwick line (East Coast route · ELR DOL1). A signaller monitors the crossing, confirms it is clear, and lowers the barriers ahead of each train. Forecasts here combine the working timetable with live train-movement data (and live signalling where the crossing has it), so they reflect actual running including delays and freight — though they can still be wrong when the network is disrupted.