Manually-controlled barrier level crossing on the Anglia route (ELR EMP).
| 00:07 | 1T70 | 🚄 | KNGX → KLYNN | → from Peterborough | +3 min |
| 00:17 | 6L34 | 🚧 | HOOJUYD → WHTMLDC | → from Peterborough | no show |
| 00:32 | 5H88 | 🚃 | ILFEMUD → CAMBCSN | → from Peterborough | no show |
| 00:34 | 2C70 | 🚆 | KNGX → CAMBDGE | → from Peterborough | +5 min |
| 00:35 | 1T72 | 🚄 | KNGX → KLYNN | → from Peterborough | no show |
| 00:37 | 9S68 | 🚄 | BRGHTN → CAMBDGE | → from Peterborough | +3 min |
| 00:43 | 2H72 | 🚆 | LIVST → CAMBDGE | → from Peterborough | -1 min |
| 00:47 | 4L61 | 🚛 | GRSTNFT → FLXSNFL | → from Peterborough | no show |
On today’s timetable, March East crossing is predicted to be closed for about 11 h 50 min between 06:00 and 22:00, across roughly 79 closures. The longest single predicted closure is 31 minutes. Freight paths scheduled “as required” — most don’t run on any given day — aren’t counted here; when one does run, the live timeline above shows it.
Closures cluster around 07:14–08:14 in the morning and around 17:26–18:26 in the evening. Gaps between closures are longest outside those windows. Other days run a different timetable, so the peaks move.
March East is a manually-controlled barrier crossing (MCB/MB) on the Ely–Peterborough line (Anglia route · ELR EMP). A signaller monitors the crossing, confirms it is clear, and lowers the barriers ahead of each train. Forecasts here combine the working timetable with live train-movement data (and live signalling where the crossing has it), so they reflect actual running including delays and freight — though they can still be wrong when the network is disrupted.
Our accuracy measurement doesn't cover this crossing yet. Reports from people at the crossing are the ground truth here. How we measure →